tankopbouw

 


 

Fase 1: Building chassis juli/augustus 2013

Herman Persyn

 

chassischassis

 

 

 

 

 

 

 

 


Fase 2: Installing Chains and engine september 2013

vandaele

 

 

tank op kettingentank op kettingen

 

 

 

 

 

 

 


Fase 3: Design and Installation tracks November 2015-2016

 

 

track

3d track

 

 

 

 

 

 

 

trackstracks

 

 

 

 

 

 

 


Fase 4: Platework april-juni 2017

 

beplatingbeplating

 

 

 

 

 

 


Fase 5: Finishing new Jcb engine maart 2018

 

JCBmotorJCB motor

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Fase 6: Changing Gardner engine with Jcb mei 2018

 

flangejcb

vervangenjcb

 

 

 

 

 

 

 

 

 

 

 

 


Fase 7: Platework roof + 1st primer juni-juli 2018

pondfarm

 

dakbeplatingbeplating

 

 

 

 

 

 

 

 

 

 

 

 

 


pondfarm

olifant

Fase 8: Painting top layer juli 2018

 

schilderen

vervaekehydrauvision

 

Fase 9: Changing Hydropumps december 2018-januari 2019

 

pompenpompen

 

 

 

 

 

 

 


pondfarm

Fase 10: Installing 3 Emergency stops/ Lights/usb connection/Camera/Remote Control

Emergency stops

 


 pondfarm

Fase 11: Finishing Male sponsons/ Sponsorplate juni 2019

sponsonsponsorplaat

 

 

 

 

 

 

 


pondfarm

Fase 12: installing shackles, spare wooden blocks september 2019

schackleswoodenblocks

 

 

 

 

 

 

 


hydrauvisionhydrauvision

Fase 13: Pressure controll cabine january 2020

 

pressurecontroll

Fase 14: Rubber Pads, chassis Nr.

Fase 15: Finishing Roof/ cabine + exhaust pipe + unditching beam